Costa Rica Expertise: Judicial fight freezes beach developments

Monday, September 19, 2005

Judicial fight freezes beach developments

By: Garland M. Baker B.
Exclusive to A.M. Costa Rica

Editor's Note: While this article was accurate at the time of publication, some information may now be outdated. We are currently preparing a comprehensive update. Sign up for our Alerts to be notified as soon as the revised content is live!

Construction of beach developments in Costa Rica has been frozen because the Sala VI constitutional court is considering a complex case that pits the central government against its employees and environmentalists.

The issue involves the concessions that developers get to build within the maritime zone, which is public land and the first 200 meters from the average high tide line. Construction is not permitted in the first 50 meters, but long-lasting concessions are permitted in the rest.  

The constitutional court is considering two actions that include a case filed by the union that represents workers in the Ministerio de Ambiente y Energía. The worker’s union is suing because the ministry changed the rules so that developers now appear to have the right to cut down some trees in the maritime zone to build hotels and other projects.

President Abel Pacheco started this internal governmental civil war with his Executive Decree No. 31750-MINAE-TUR published May 14, 2004, in La Gaceta, the official public records newspaper, No. 96. Also involved in the document was the minister of Turismo, Rodrigo Castro, and the environmental minister, Carlos Manuel Rodríguez.

At stake is the definition of “ecotourism.” The workers union and many environmentalists do not agree with the definition expressed in a year-old decree. The decree modified the definition of “ecotourism,” saying the word now means something that contributes to the welfare of residents nearby and encourages exploitation of the natural and cultural heritage.

An earlier definition of ecotourism put research first and tourism second. It said nothing about cutting down trees.

The 2004 decree permits developers to cut down trees for ecotourism development, some 15 percent of primary forest and 25 percent of secondary forest that happened to be in the maritime zone.
 
Around the same time as this decree was promulgated and on another front, the environmental minister requested the Procuraduría General de la República, the nation's lawyer, to clarify who regulates concessions in the maritime zone. The answer, much to the surprise of everyone, was his ministry. This took the power away from the municipalities that have been granting the concessions.

Environmentalist immediately attacked and so did the municipalities. Each party has a different reason. The municipalities do not want to lose the power they have had. The environmentalists want to avoid seeing any more trees cut down in Costa Rica. The country has been severely deforested in the past 50 years. 
 
Rodríguez admitted to pressure from Casa Presidencial in two interviews with the press to allow accelerated cutting of trees in the maritime zone. 
 
Two cases were filed with the Sala IV on this issue. One in May 2004, shortly after the decree, was filed by FECON, the Costa Rican Federation for the Conservation of Natural Resources. 

The other was filed in June 2004 by the workers union of the environmental ministry, called the Asociación Sindical de Trabajadores del Ministerio del Ambiente y Energía y Afines de Conservación.

What happens now for all those developers waiting on a concession in the maritime zone?
That answer is in the hands of the constitutional court.  The two cases above have been joined by the court and accumulated as No. 04-005607-0007-CO.

To be or not to be, to cut down trees or not to cut down trees in the maritime zone, that is the question.  There will be no definite answer anytime soon.  Even when there is, more fights will arise because the issue is at the heart of very opposing viewpoints of Costa Rica’s future development and the meaning of progress.

Therefore, this means a long time may pass before another maritime concession is approved in Costa Rica.

Article first published in A.M. Costa Rica on September 19, 2005.